View on leginfo.ca.gov(a)For purposes of establishing rates for any electrical or gas corporation, the commission shall disallow expenses reflecting the direct or indirect costs resulting from any unreasonable error or omission relating to the planning, construction, or operation of any portion of the corporation’s plant which cost, or is estimated to have cost, more than fifty million dollars ($50,000,000), including any expenses resulting from delays caused by any unreasonable error or omission. Nothing in this section prohibits a finding by the commission of other unreasonable or imprudent expenses. This subdivision is a clarification of the existing authority of the commission, is not intended to limit or restrict any power or authority of the commission conferred by any other provision of law, and applies to all matters pending before the commission. This section does not prohibit the commission from establishing rates for an electrical or gas corporation on a basis other than an allowed rate of return on undepreciated capital costs.
(b)Whenever an electrical or gas corporation fails to prepare or maintain records sufficient to enable the commission to completely evaluate any relevant or potentially relevant issue related to the reasonableness and prudence of any expense relating to the planning, construction, or operation of the corporation’s plant, the commission shall disallow that expense for purposes of establishing rates for the corporation. This subdivision does not apply where the commission determines that a reasonable person could not have anticipated either the relevance or potential relevance, to an evaluation of costs incurred on the project, of preparing or maintaining the records or the extent of recordkeeping required to adequately evaluate those costs.
(c)For purposes of this section:
…
Legislative history
Added by Stats. 1985, Ch. 1212, Sec. 1.