DecisionDepot
California legal research

California Public Utilities Code

§ 1003

PUC § 1003Div. 1 · Part 1 · Ch. 5 · Art. 1
Every electrical and every gas corporation submitting an application to the commission for a certificate authorizing the new construction of any electric plant, line, or extension, or gas plant, line, or extension, not subject to the provisions of Chapter 6 (commencing with Section 25500) of Division 15 of the Public Resources Code, shall include all of the following information in the application in addition to any other required information:
(a)Preliminary engineering and design information on the project. The design information provided for thermal electric plants shall include preliminary data regarding the operating characteristics of the proposed plant, including, but not limited to, the annual capacity factor, availability factor, and the heat rate for each year of the useful life of the plant, line, or extension.
(b)A project implementation plan showing how the project would be contracted for and constructed. This plan shall show how all major tasks would be integrated and shall include a timetable identifying the design, construction, completion, and operation dates for each major component of the plant, line, or extension.

Legislative history

Added by Stats. 1982, Ch. 1253, Sec. 2.

Source: California Public Utilities Code § 1003 from the California Legislative Information (public record). DecisionDepot is for informational use only and is not legal advice — verify against the official source before relying on this text.