View on leginfo.ca.govFor purposes of this chapter, the following definitions apply:
(a)“Alternative project delivery method” means either Construction Manager/General Contractor method or design sequencing.
(b)“Construction Manager/General Contractor method” or “CMGC” means a project delivery method using a best value procurement process in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
…
Legislative history
Added by Stats. 2012, Ch. 767, Sec. 1. (SB 1549) Effective January 1, 2013.